Definition

Hydrogeology – area of geology that deals with the distribution and movement of groundwater in the soil and rocks of the Earth’s crust (commonly in aquifers)

Reasons for carrying out the survey

The hydrogeological assessment typically comprises of (but is not limited to) the following tasks:

  • Ascertain the requirements of the client, location, yield and use
  • Hydrogeology, implications of the geology in terms of water bearing horizons, anticipated yield, hydraulic properties of each aquifer, groundwater flow direction, pathways and rates of flow.
  • Boreholes and abstractions in the catchment and region, including borehole logs and aquifer parameters (where known)
  • Catchment risk assessment, and risks to yield and quality, including the potential for planned activities to result in groundwater contamination and known or expected presence, distribution, concentration and risk from existing contamination.
  • Anticipated yield and quality of abstracted water
  • Borehole design and recommendations
Setting up for a hydrogeological survey in Uganda
Setting up for a hydrogeological survey
Terrameter used in hydrogeological survey
Terrameter used in hydrogeological survey

General survey report contents

Hydro geological survey report is based on the findings observed while carrying out survey, it contains the following:

  • Expected quantity of water and recommended drilling depth
  • Geology map showing point(s) location
  • Topographic map*
  • Line profile data and map*
  • Existing Borehole data analysis
  • Vertical Electrical Sounding results for the sites selected for drilling
  • Some information of interest to Client
An example of a geological map - Borehole survey in Uganda
An example of a geological map of a surveyed and recommended drilling point
Example of borehole design in Uganda
Example of borehole design one
An example of borehole design
Example of borehole design two

Selected past borehole surveys

Find a few selected past hydrogeological (borehole) survey projects

1. Borehole survey in Nakivale -1

Purpose of the survey

  • Determine best drilling points for three production boreholes to provide water for community use
PointEstimated yield(m3/hr)Recommended drilling depth(m)
Borehole point 13120
Borehole Point 23120
Borejole point 310150

Some field photos

2. Borehole survey in Jinja

Purpose of the survey

  • Well to supply water for domestic use
Estimated yield(m3/hr)Recommended drilling depth(m)
3100

Some field photos

3. Borehole survey in Masaka

Purpose of the survey

  • Well to supply water for use at the organization
Estimated yield(m3/hr)Recommended drilling depth(m)
4120

Some field photos

4. Borehole survey in Nakivale 2

Purpose of the survey

  • Well to supply water for the community
Estimated yield(m3/hr)Recommended drilling depth(m)
290

Some field photos

5. Borehole survey in Masindi

Purpose of the survey

  • Well to supply water for the community
Estimated yield(m3/hr)Recommended drilling depth(m)
485

Some field photos

  • Borehole survey for a production borehole in Masindi
  • Borehole survey in Masindi
  • Hydrogeological survey in Masindi
  • Pegging a borehole drilling point

6. Borehole survey in Yumbe 1

Purpose of the survey

  • Well to supply water for the community
Estimated yield(m3/hr)Recommended drilling depth(m)
270

Some field photos

7. Borehole survey in Yumbe 2

Purpose of the survey

  • Well to supply water for the community
Estimated yield(m3/hr)Recommended drilling depth(m)
170

Some field photos

Need more information about borehole survey in Uganda? Contact Us